General Technical Information
Amount of waste taken in | 96 000 tons/ year |
Reduction of waste | Weighed at 1/3, by volume 1/10 |
Operation time | 8 000 hours/ year |
Heat out-put:
Heat discharge into the central system supply of heat in Liberec | 38,3 MW |
Presumed supply and sale of heat | 700 000 GJ / year |
Steam parameters(vapor) | 10 bar / 2300 °C |
Production of electrical energy:
Electrical discharge back-pressure turbine | 3,5 MW + 1 MW |
Discharge of electric energy supplied into an electrical current | 2 – 3 MW |
Presumed supply and sale of electrical energy | 13 000 MWh / year |
This gives rise to the reduction of oil used by the heat station in Liberec, a.s. |
Approx 20 000 t / year |
Incinerator project author and technical supervisor and investor: |
E.I.C., spol. s r. o. |
Producer of the Incinerator: | consortium Škoda TS a.s. Plzeň and Von Roll (Switzerland) |
Investor and operator of the Incinerator: | Termizo, a.s. |
The plant fills all regulations in relationship to the environmental specifications in the Czech Republic and the EU and complies with modern European trends in waste disposal.